Page 39
California. Supreme Court. a recovery of actual damges , so that no more , perhaps , can be recovered than the sum named in the penalty . In cases of penalty the penalty is not a debt ; the recital of a contract containing the penalty is ...
California. Supreme Court. a recovery of actual damges , so that no more , perhaps , can be recovered than the sum named in the penalty . In cases of penalty the penalty is not a debt ; the recital of a contract containing the penalty is ...
Page 66
... actual value of the work and material was more than the estimates made by the engineer ; was , in fact , about $ 360,690 . The court found that the value of the labor and materials was $ 285,918.49 . It would seem , therefore , that 66 ...
... actual value of the work and material was more than the estimates made by the engineer ; was , in fact , about $ 360,690 . The court found that the value of the labor and materials was $ 285,918.49 . It would seem , therefore , that 66 ...
Page 72
... actual amount was increased or diminished . It was further stipulated that , in case certain bonds were is- sued by named counties to aid the corporation to construct the road , " all work done and materials furnished , and all other ...
... actual amount was increased or diminished . It was further stipulated that , in case certain bonds were is- sued by named counties to aid the corporation to construct the road , " all work done and materials furnished , and all other ...
Page 74
... actual quantities of work performed . " The contract between Cox and Arnold and the engineer , it is said , was terminated about the time McLaughlin was expected to return from the East , after three or four esti- mates had been made ...
... actual quantities of work performed . " The contract between Cox and Arnold and the engineer , it is said , was terminated about the time McLaughlin was expected to return from the East , after three or four esti- mates had been made ...
Page 78
... actual value of the labor performed was , under the circumstances , an abuse of discretion , which ought to be reviewed by this court . This litigation has been pending for some sixteen years , during all of which time plaintiffs had ...
... actual value of the labor performed was , under the circumstances , an abuse of discretion , which ought to be reviewed by this court . This litigation has been pending for some sixteen years , during all of which time plaintiffs had ...
Contents
318 | |
355 | |
386 | |
387 | |
394 | |
395 | |
404 | |
460 | |
116 | |
125 | |
131 | |
136 | |
169 | |
230 | |
242 | |
255 | |
281 | |
291 | |
294 | |
305 | |
469 | |
494 | |
508 | |
521 | |
567 | |
578 | |
587 | |
618 | |
626 | |
631 | |
659 | |
Other editions - View all
Common terms and phrases
action was brought adverse possession affidavit affirmed agreement alleged amended appeal Appellant application assessment attorney auditor bill of exceptions cause of action city and county Civil Code Civil Procedure claim Code Civ Code of Civil complaint concurred contract corporation counsel county of San damages deed defendant defendant's demurrer effect entitled error estoppel evidence facts favor fendant filed grant held homestead hundred dollars insured issued judge judgment and order jury Kings River land lien mandamus MCFARLAND MCKINSTRY ment mortgage motion Note citations notice opinion order denying order refusing owner paid parties payment person plaintiff possession premises purchase quantum meruit question railroad real property recover Respondent San Francisco SEARLS SHARPSTEIN sheriff statement statute statute of limitations street sufficient Superior Court sustaining thereof thousand dollars tiff tion tract trial void writ